Dean and his team have been laying the facing bricks this week and have matched the height of the internal block wall leaving only 3 feet or so to go. I was surprised to see him there today (Sunday) but apparently he wanted to finish the bay to bottom of window height before the scaffolders arrive tomorrow. Unfortunately Dean's team are all on annual holiday this coming week which will mean that he will have one week to finish the brickwork before the carpenter arrives to fix the roof trusses. Its cutting it a bit fine - we'll have to pray for good weather week commencing 24th August!
No other news at the moment - all's quiet on the access drive front.
Jan & Rog