The (wet) shower room
The bathroom (nearly finished)
The other half of the bathroom
Our "disabled" ramp and pea grit area... we could get rid of that damn portable toilet! But Anglian Water are not shifting - they refuse to provide any significant water pressure - just the 1/2 litre an hour that trickles through. This means that our bathroom fitters can't test their pipework and so we end up with all the pipes boxed in and tiled, hoping there are no leaks. Monopolies - I hate them.
~Anyway, that apart, Vic and Dave our two bathroom fitters have transformed the bathroom and shower room as you can see from the pictures above. Dave (tiling) set about tiling those walls that Vic (plumber) needed to fit things to, so they swapped rooms so each could carry out their own bits of the work. Tuesday brought some bad news though - we had been sent the wrong toilet for the shower room. Instead of the "3/4 back" one ordered we had been sent a "back-to-the-wall" jobby. I raced back to the supplier in Bedford on Tuesday with the wrong toilet/cistern, hoping they would have the correct one in stock. But no, they didn't. Blast! Worse still, the correct one might not arrive until next week, well after Vic and Dave had expected to finish. Fortunately, as it turned out, one was found (somewhere) and duly delivered for Vic to fit on Saturday. We're really pleased with the appearance of both rooms, and with the benefit of white tiles on the walls, both look light and bright. Unfortunately, we were some tiles short for the bathroom, and due to the bank holiday, will have to wait until Wednesday next week for the delivery.
~We had confirmation on Wednesday that our stairs are en route from Poland and will be fitted on the bank holiday Monday. The meant that I had to varnish the woodwork in the lounge before the stairs were installed as I would have difficulty reaching some of the skirting with the stairs in situ. That was my Saturday mapped out then!
~Also this weekend (Sunday now), Tony, our plasterer, is going to render the fireplace. Jan thinks I've gone a bit over the top on this as I wanted the corners to be round and not square (I was only thinking of the ease of cleaning - really). This meant I had to make up formers to create the "roundness" and Tony will be building up layers of "stuff" over my formers. That has reminds me that I need to buy some more pamments as we intend to use the ones left over from the porch, but will need four more.
~
Wednesday produced another upset - the kitchen supplier told us that they could not longer get the material for the doors we had chosen. This meant that the quadrant shape cupboards at the "breakfast bar" end of the kitchen would have to become square. That's a real shame, but Jan felt the substitute she had chosen was the best compromise. I guess it will give us slightly more cupboard space though. On the subject of kitchens, Nigel the kitchen planner visited on Tuesday to double check the measurements and make sure that his boss's figures were correct. Production of the kitchen and worktop starts next week with fitting still scheduled for week commencing 17th May.
~With the absence of rain we had become a little concerned about our hedgerow plants. Some seemed to be doing OK in their plastic spirals, but about 30% seemed less than happy with no sign of growth at all. We cut down the spirals of those that looked healthy to give them room to expand, and removed the spirals from those that looked dead. However, when Jan pruned back some of the "dead" ones, the wood was green, so perhaps there is life there and we're being impatient. The rain this weekend should help.
~One little tale that restores ones faith in the stupidity of some areas of the building trade - I ordered four bags of walling and bonding material for Tony on Monday, with instructions that the bags should be put in the garage where I had cleared a space. Where did the driver leave them? Why, in the middle of the flower bed that Jan and I had spent some time digging, fertilising and raking at the weekend. Beggars belief, doesn't it? Even ignoring the instruction to leave the material in the garage, he had the choice of a paved area, a gravelled area, the lawn, and an obviously recently-dug flower bed. All were equally easy to unload on, but he chose the flower bed - DOH!
~As we are cannibalising the units we plan to put in the utility room (to make them fit where our architect mucked up the room size) we opted for a range of units from IKEA. Having visited their Milton Keynes store last week to check out the different styles, we went back on Thursday evening for our second helping of meatballs (did you know that globally, IKEA sell 43 million Swedish meat balls a year? No? Well you can impress your friends with that gem!) and we ordered the units, worktop, and sink. Jon our very capable amateur kitchen fitting friend, will then set about modifying them for us.
~
Jan & Rog





